> For the complete documentation index, see [llms.txt](https://grid-insight-technology-pvt-ltd.gitbook.io/into-the-grid/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://grid-insight-technology-pvt-ltd.gitbook.io/into-the-grid/almm-list-ii-from-june-2026-what-solar-developers-epcs-and-consumers-need-to-know.md).

# ALMM List-II from June 2026: What Solar Developers, EPCs and Consumers Need to Know

<figure><img src="https://3076575087-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FdKRnDcia2uPF5l0O35Af%2Fuploads%2FlYdW1OTzTfPlcY4ZBcOA%2Fpexels-kelly-4320449.jpg?alt=media&amp;token=c01b2ebb-4651-4afa-88f6-2476a32048fd" alt=""><figcaption></figcaption></figure>

### The Indian Solar Industry Enters a New Phase

Over the past few months, one question has dominated discussions across the solar industry:

"Will non-DCR solar modules be banned after June 2026?"

The answer is both simple and nuanced.

The Ministry of New and Renewable Energy (MNRE) has now confirmed that from 1 June 2026, projects covered under specific government schemes and regulatory frameworks must comply with the Approved List of Models and Manufacturers (ALMM) List-II requirements. In practical terms, this means that eligible projects will need to use modules manufactured using approved domestic solar cells.

While many market participants have interpreted this as a complete ban on non-DCR modules, the actual position is more specific. Understanding where these requirements apply—and where they do not—is essential for project developers, EPC contractors, commercial consumers, and investors planning solar installations over the coming years.

#### &#x20;What is ALMM List-II?

The Approved List of Models and Manufacturers (ALMM) was introduced by MNRE to promote quality assurance, traceability, and domestic manufacturing within India's rapidly growing solar sector.

ALMM List-I focuses on approved solar module manufacturers, while ALMM List-II covers approved solar cell manufacturers.

From June 2026 onwards, projects falling under the scope of the mandate must ensure that the modules installed are manufactured using cells sourced from ALMM List-II approved facilities.

The objective is clear: strengthen India's domestic solar manufacturing ecosystem, reduce import dependency, and improve supply chain security for strategic energy infrastructure.

#### &#x20;Which Projects Are Covered?

The mandate applies to a significant portion of India's solar market, including:

<table data-view="cards"><thead><tr><th></th><th data-hidden data-card-cover data-type="image">Cover image</th></tr></thead><tbody><tr><td>Government Solar Tenders</td><td><a href="https://3076575087-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FdKRnDcia2uPF5l0O35Af%2Fuploads%2FtL1MmJJnDJbEp4JX0vKQ%2FPM-Modi-Solar-panel-04.jpg?alt=media&amp;token=459fecee-7a9e-4bae-8af6-0e42e05c6f21">PM-Modi-Solar-panel-04.jpg</a></td></tr><tr><td>PM Surya Ghar Residential Rooftop Projects</td><td><a href="https://3076575087-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FdKRnDcia2uPF5l0O35Af%2Fuploads%2FuwMxFkG4REg2PJoXJbRT%2FPM-Surya-Ghar-Yojana-2026-Updated-Subsidies-Eligibility-How-to-Apply-What-is-PM-Surya-Ghar-Yojana%201.png?alt=media&amp;token=fb602a46-9858-4350-b5a3-25f9847e0382">PM-Surya-Ghar-Yojana-2026-Updated-Subsidies-Eligibility-How-to-Apply-What-is-PM-Surya-Ghar-Yojana 1.png</a></td></tr><tr><td>PM KUSUM Component B and Component C projects</td><td><a href="https://3076575087-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FdKRnDcia2uPF5l0O35Af%2Fuploads%2F8q9QIR0U4VTPtfZlk1zC%2FUntitled-design-27.jpg.bv_resized_mobile.jpg.bv.webp?alt=media&amp;token=905a7ea5-b343-442d-a230-7583b6c65ea0">Untitled-design-27.jpg.bv_resized_mobile.jpg.bv.webp</a></td></tr><tr><td>Open Access Solar Projects</td><td><a href="https://3076575087-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FdKRnDcia2uPF5l0O35Af%2Fuploads%2FDOE4DF3FFP4Xcuyl5Aln%2Fpexels-quang-nguyen-vinh-222549-35105443.jpg?alt=media&amp;token=33b498a6-8587-4aed-bb8a-0cad88e073aa">pexels-quang-nguyen-vinh-222549-35105443.jpg</a></td></tr><tr><td>Net-metered Rooftop Solar Installations</td><td><a href="https://3076575087-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FdKRnDcia2uPF5l0O35Af%2Fuploads%2FRMVUwq0YvAgdOSe3e8cw%2F10kw-ongrid-solar-installation.jpg?alt=media&amp;token=3fcd904e-2843-4d54-9245-f639dcf19f2a">10kw-ongrid-solar-installation.jpg</a></td></tr><tr><td>Projects Seeking Benefits Under Government Support Schemes</td><td><a href="https://3076575087-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FdKRnDcia2uPF5l0O35Af%2Fuploads%2Fssw5HTQwhfPqkzRpTlCt%2Fimage%20147.png?alt=media&amp;token=f03ef36e-74f7-40cd-91e6-a4a18845abde">image 147.png</a></td></tr></tbody></table>

For these projects, compliance with ALMM List-II requirements will be mandatory for systems commissioned after 1 June 2026.

Developers planning installations under these categories should review procurement plans immediately and verify compliance with suppliers before placing orders.

#### Are Non-DCR Modules Completely Banned?

No. A common misconception is that non-DCR modules will disappear from the Indian market after June 2026. This is not currently the case.

Certain private commercial and industrial (C\&I) projects that operate purely behind the meter and do not seek subsidies, net-metering benefits, or government incentives may continue to have flexibility regarding module selection.

However, regulations continue to evolve, and project-specific assessments remain essential. Developers should consult with experienced EPC partners before finalising procurement decisions.

The key takeaway is that the June 2026 transition is a compliance requirement for specific project categories—not a universal ban across every solar installation in India.

<figure><img src="https://3076575087-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FdKRnDcia2uPF5l0O35Af%2Fuploads%2FCh3Vjo5RLeMVvIxlroNY%2FChatGPT%20Image%20Jun%208%2C%202026%2C%2003_12_03%20PM%201.png?alt=media&amp;token=b84bc9a9-7133-4231-a180-ff0cdc03d8f9" alt=""><figcaption></figcaption></figure>

#### Why This Matters for Project Economics

The impact of the new requirements extends beyond compliance.

India's total solar module manufacturing capacity has expanded rapidly over the past few years. However, domestic cell manufacturing capacity approved under ALMM List-II remains significantly lower than total module production capacity.

**This creates an important market dynamic:**

* Higher demand for compliant modules
* Longer procurement lead times
* Potential pricing pressure
* Greater importance of early procurement planning
* Increased focus on supplier verification

For developers and EPC contractors, waiting until the final stages of project execution to secure module supply may create unnecessary risks.

The projects most likely to face challenges are not those lacking demand, but those that underestimate supply chain constraints.

#### The Growing Importance of Supplier Verification

One of the most significant changes introduced alongside the ALMM framework is enhanced traceability.

Manufacturers supplying DCR-compliant modules are now required to provide unique verification documentation through the national DCR verification system.

This means EPC companies can no longer rely solely on manufacturer declarations or marketing claims.

**Before finalising procurement, project stakeholders should verify:**

* Current ALMM registration status
* Approved manufacturing facilities
* Eligible cell technologies and models
* Traceability documentation availability
* Compliance with the latest MNRE notifications

A supplier's status can change as ALMM revisions are periodically updated, making real-time verification critical.

#### Commissioning Timelines Have Become More Important Than Ever

Another important consideration is project commissioning.

Many rooftop projects across India are physically completed but continue to await inspections, approvals, and commissioning certificates from local authorities and DISCOMs.

For projects nearing completion, administrative delays can now become a compliance risk.

Developers and EPC contractors should actively monitor pending approvals, maintain regular communication with DISCOM officials, and ensure that all documentation is submitted correctly and on time.

Strong project management during the commissioning phase may prove just as important as technical execution.

### What Should EPCs and Developers Do Now?

As the industry transitions into the ALMM List-II era, the most successful organisations will be those that act proactively.

{% stepper %}
{% step %}
**Review Your Project Pipeline**

Identify all projects expected to be commissioned after June 2026 and determine whether they fall within the scope of the mandate.
{% endstep %}

{% step %}
**Verify Supplier Compliance**

Confirm that module and cell suppliers appear on the latest approved ALMM lists and can provide required documentation.
{% endstep %}

{% step %}
**Secure Supply Early**

Avoid last-minute procurement decisions that may expose projects to availability constraints or price fluctuations.
{% endstep %}

{% step %}
**Monitor Commissioning Milestones**

Ensure all inspections, approvals, and utility interactions are tracked closely to prevent avoidable delays.
{% endstep %}

{% step %}
**Educate Customers**

Many customers remain uncertain about the impact of the new regulations. EPCs that provide clear guidance will build greater trust and strengthen long-term relationships.
{% endstep %}
{% endstepper %}

### Looking Ahead

The June 2026 ALMM List-II implementation represents more than a regulatory milestone—it signals the next phase of India's solar manufacturing journey.

As domestic cell production expands and supply chains mature, the industry is expected to become more resilient, traceable, and aligned with the nation's long-term energy security goals.

For developers, investors, and solar consumers, the message is straightforward:

The opportunity remains enormous, but project planning, procurement strategy, and compliance management will become increasingly important.

Organisations that adapt early will be best positioned to maintain project schedules, protect margins, and continue delivering high-quality solar installations in India's evolving renewable energy landscape.

#### Need Guidance on ALMM-Compliant Solar Projects?

Bijlee Solar helps commercial, industrial, institutional, and government clients navigate changing solar regulations while delivering reliable, bankable solar solutions.

Whether you're planning a rooftop installation, open access project, PM KUSUM deployment, or utility-scale solar plant, our team can help you evaluate compliance requirements, optimise procurement strategy, and execute projects with confidence.

\
\ <br>

<br>

<br>

<br>